| Project
Scope: |
| 1. |
Widen
existing Old Winston Road to three lanes and curb and gutter. |
| 2. |
Provide a center
turning lane for the entire length of the project. |
| 3. |
Realign the Oakview
Road and Old Winston Road intersection. |
| 4. |
Realign the East
Bellevue Drive and Old Winston Road intersection. |
| 5. |
Realign the North
Main Street and East Bellevue Drive intersection. |
| 6. |
Add turn lanes
at the following intersections:
| a. |
North
Main Street and Old Winston Road (two westbound turn
lanes). |
| b. |
Oakview
Road and Old Winston Road. |
| c. |
Shadybrook
Road and Old Winston Road. |
|
| 7. |
Provide 5' concrete
sidewalks on both sides of Old Winston Road. |
| 8. |
Provide a storm
drainage system along Old Winston Road. |
| 9. |
Proposed to begin
purchasing right-of-way and construction easements in summer
2006. |
| 10. |
Proposed to begin
utility relocation work once right-of-way and easements are
secured. |
| 11. |
Proposed to begin
construction during 2007. |